Centorum
Gujranwala Electric Power Company

Controlling Document Queue

Position at 6 Jun 2026
  
Issues flagged13
Blocking4
Value affectedRs4,228,100,000
StatusSupplierContractInstrumentAt riskSeverityTop IssueInstrument type
ON HOLDSialkot Electrical WorksGEPCO/SKT/DW-IND/2026-03VO-01/2026Rs5,900,000High
Variation issued without a costing or a revised demand notice
Authority & approval
Variation order
ON HOLDTariq Electric StoreGEPCO/GRT/HW-QTN/2026-07SO/GRT/2026/014-022Rs21,600,000High
Nine orders between Rs 2,150,000 and Rs 2,480,000, same supplier, same items
Procurement validity
Supply order
ON HOLDChenab Transformers (Pvt) LtdGEPCO/MM/DT-100/2026-14LOA/MM/2026-14Rs1,840,000,000High
Both rejections rest on clause 4.2 and no other ground
Procurement validity
Letter of acceptance
ON HOLDRavi Power Construction Co.GEPCO/GRW/OH-RECON/2026-08WO/GRW/2025/1187Rs412,000,000High
Work order says existing route and supports; the record says realigned with 214 new poles
Instrument consistency
Work order
PENDINGKohinoor Conductors LtdGEPCO/MM/ACSR/2026-11PAC-03/2026Rs41,300,000Medium
Certificate uses an October base; the contract fixes August 2025
Instrument consistency
Price adjustment certificate
PENDINGSialkot Electrical WorksGEPCO/SKT/DW-IND/2026-03VO-01/2026Rs5,900,000Medium
Bay was erected before the variation was issued
Authority & approval
Variation order
PENDINGTariq Electric StoreGEPCO/GRT/HW-QTN/2026-07SO/GRT/2026/014-022Rs21,600,000Medium
Items were available on the annual materials plan
Procurement validity
Supply order
PENDINGRavi Power Construction Co.GEPCO/CON/11KV-NEW/2026-04WO/CON/2026/0289Rs337,000,000Medium
Prequalification expires 30 June 2026; the work order runs to Feb 2027
Authority & approval
Work order
PENDINGIndus Grid Engineering (Pvt) LtdGEPCO/GSO/132-BAY/2025-22EOT-02/2026—Medium
Guarantee still runs to the original completion date, 14 July 2026
Authority & approval
Extension of time
PENDINGIndus Grid Engineering (Pvt) LtdGEPCO/GSO/132-BAY/2025-22EOT-02/2026—Medium
Milestone schedule at Annex C still carries the original dates
Instrument consistency
Extension of time
PENDINGPunjab Metering Systems (Pvt) LtdGEPCO/MM/AMI-MTR/2026-09CO/MM/2026-09Rs1,044,000,000Medium
Lots 3 and 4 taken on charge with no inspecting officer's report
Authority & approval
Purchase order
PENDINGFrontier Safety SuppliesGEPCO/NRW/TP-SAFE/2026-02SO/NRW/2026/003Rs41,300,000Medium
Request for quotations used well above its ceiling
Procurement validity
Supply order
PENDINGSarwar Transport ServicesGEPCO/HFZ/OM-VEH/2025-31SO/HFZ/2025/031Rs64,800,000Medium
No instrument exists to carry the service past 14 July
Authority & approval
Work order