Centorum
Gujranwala Electric Power Company

Contract Obligation Queue

Position at 6 Jun 2026
Open alerts16
Overdue9
Due soon7
StatusSeveritySupplierContractObligationDueReminders
Overdue· 159d overdueHighChenab Transformers (Pvt) LtdGEPCO/MM/DT-100/2026-14Technical schedule fixes a tank height only one prequalified maker builds, and two of three bids fell on it29 Dec 20259 overdue notices sent
Overdue· 67d overdueHighMeridian Power ConsultantsGEPCO/PND/LOAD-SUR/2026-06Load flow model for three circles overdue by 67 days with the next instalment held31 Mar 20269 overdue notices sent
Overdue· 62d overdueHighSialkot Electrical WorksGEPCO/SKT/DW-IND/2026-03Deposit works overspent by Rs 5,900,000, which falls on GEPCO unless a revised notice is raised5 Apr 20269 overdue notices sent
Overdue· 61d overdueLowMeridian Power ConsultantsGEPCO/PND/LOAD-SUR/2026-06No monthly progress report since February, the same months the overdue deliverable slipped in7 Apr 20269 overdue notices sent
Overdue· 47d overdueHighRavi Power Construction Co.GEPCO/GRW/OH-RECON/2026-08Rs 318,000,000 of rebuilt feeder booked to maintenance, so the new line sits on no asset register20 Apr 20269 overdue notices sent
Overdue· 41d overdueHighPunjab Metering Systems (Pvt) LtdGEPCO/MM/AMI-MTR/2026-0940,000 meters taken on charge against the delivery challan alone, with no stores inspection report26 Apr 20268 overdue notices sent
Overdue· 33d overdueMediumRavi Power Construction Co.GEPCO/GRW/OH-RECON/2026-0831 km of conductor and 214 poles dismantled and never returned to store against a salvage note4 May 20267 overdue notices sent
Overdue· 26d overdueMediumKohinoor Conductors LtdGEPCO/MM/ACSR/2026-11Escalation computed from the wrong base month, understating the supplier's claim by Rs 6,800,00011 May 20265 overdue notices sent
Overdue· 22d overdueMediumJhelum Valley BuildersGEPCO/MBD/CIVIL-GS/2025-19Final bill presented with nine handover defects open, so Rs 3,530,000 of retention cannot be released15 May 20264 overdue notices sent
Due Soon· 15d leftMediumRavi Power Construction Co.GEPCO/CON/11KV-NEW/2026-04All risks and workmen's cover lapses on 21 June with line crews still working at height21 Jun 2026Scheduled
Due Soon· 24d leftMediumRavi Power Construction Co.GEPCO/CON/11KV-NEW/2026-04Contractor's prequalification lapses on 30 June, and the contract bars further payment once it does30 Jun 2026Reminder sent
Due Soon· 38d leftHighIndus Grid Engineering (Pvt) LtdGEPCO/GSO/132-BAY/2025-22Performance guarantee expires 78 days before the revised completion date14 Jul 2026Reminder sent
Due Soon· 38d leftHighSarwar Transport ServicesGEPCO/HFZ/OM-VEH/2025-31Circle's hired vehicles lose their contract in 38 days, and it allows no extension to bridge the gap14 Jul 2026Reminder sent
Due Soon· 51d leftMediumChenab Transformers (Pvt) LtdGEPCO/MM/DT-100/2026-14Transformer maker's prequalification expires with Rs 1,150,000,000 still to deliver against it27 Jul 2026Reminder sent
Due Soon· 74d leftLowChenab Line ConstructorsGEPCO/GRT/LT-AB/2026-05Works insurance names only the contractor, so GEPCO cannot claim on cover for its own works19 Aug 2026Scheduled
Due Soon· 116d leftMediumSialkot Electrical WorksGEPCO/SKT/DW-IND/2026-03Deposit completion account due 29 November, and it cannot be closed until the excess is recovered29 Nov 2026Scheduled

Invoices, findings, and contract scenarios shown are simulated for demonstration purposes and do not represent actual vendor conduct.